Search This Blog

Wednesday, December 19, 2012

KKIA runway unsafe


Work has stopped following dispute with Transport Ministry over money

KOTA KINABALU: Global Upline Sdn Bhd (GUSB), the contractor for the Kota Kinabalu International Airport's (KKIA) runway expansion and resurfacing of the existing runway announced it had stopped work effective last Monday, following a financial dispute with the Ministry of Transport (MoT).

"In the interest of safety to aircraft operation and passengers alike, we would like to inform the public that the runway is not safe for landing, take-off and other operations since it has been certified non-complete by MoT," claimed GUSB Chief Adviser, Tan Sri Ting Pek Khing.

He said it was a common fact that the New Extended Runway and Resurfaced Existing Runway had been in use since April 2012 and by May 1, 2012, while the airport operates on a 24-hour basis.

He said the MoT had promised during a meeting in January 2012 that it would issue the Certificate of Practical Completion (CPC) and release 50 per cent of Banker's Guarantee if GUSB could complete Section-1 Works by April 30, 2012.

Ting said that by April 30, 2012, GUSB had practically completed Section-1 Works.

"This was achieved because GUSB had used his best financial endeavours and utilised his utmost available resources. MoT however reneged on their promise and refused to issue the CPC and subsequently release 50 per cent of the Banker's Guarantee.

"Instead, MoT issued a Certificate of Non-Completion (CNC) and imposed Liquidated Damages (LAD) claim despite the completed works having been in use ever since April 5, 2012, inter alia the new Runway Extension, Resurfaced Existing Runway, New Taxiway 'K', New Southern Taxiway 'C', New Taxiway 'E', New Taxiway 'D' and Resurfaced Taxiway 'A'," he said.

Currently, the total runway length available in KKIA is 3,000 metres and a seven-kilometre HT cable was completed and all three pump stations operated on automation.

"We have written several letters since June 2012, including to the Prime Minister asking and demanding MoT and/or Project Management Consultant (PMC) to reply and resolve the issue pertaining to the CPC and other issues affecting the completion of KKIA," he said.

But, neither MoT nor the PMC had replied or took action on issues brought to their attention until recently, on Dec 10, 2012 when instead MoT issued a notice for GUSB to complete the KKIA project within 14 days, failing which the GUSB contract would be terminated.

"It is unrealistic and impossible to complete construction works worth RM50 million within two weeks.

"At this juncture, GUSB challenged MoT's Secretary General to complete the works within three weeks after a new contractor is appointed.

Failing which, the Secretary General should undertake total responsibility on its consequences."

Ting also said that the Minister of Transport had not been on the ground to see the actual facts on site. "Hence, he does not use eyes, but uses his ears to see and relies on them to make decision(s)," he said.

The MoT was not keen to see GUSB complete the project at KKIA and intended to appoint others instead by intentionally and purposely fabricating motives to cause willful damage and injured GUSB's financial position, he claimed.

Apart from refusing to issue the CPC, and refusing to release 50 per cent of the Banker's Guarantee and imposong the LAD claim for the KKIA project, he said the Ministry also refused to pay RM113 million contractual claim for Kuching International Airport and retained RM21 million for the Labuan Airport, both projects done by GUSB.

"All of it was done in bad faith to disqualify GUSB. GUSB was left with no choice but to commence legal proceedings to recover our money for the Kuching International Airport project and Labuan Airport project," he said.

According to Ting, GUSB would undertake to complete KKIA within six months if the MoT kept its promise to issue the CPC and release 50 per cent of the Banker's Guarantee.

"When completed, it is GUSB's assurance that it will be well within the allocated Contract Sum without any additional claim or cost extra taxpayer's money to the government.

"We have RM100 million worth of machinery at the project site.

The balance contract amount is RM37 million and the Banker's Guarantee is RM36 million.

"We completed KKIA Terminal 2 building in record time (completed in six months compared to the scheduled 18 months).

We also completed two fly-overs and roadworks in Kota Kinabalu despite not receiving prompt payment from the government.

"GUSB has repeatedly brought this matter to MoT but without avail.

GUSB now broadcasts the matter to the public and leaves it to the good judgement of the public," he said.

16 comments:

  1. The addition of a new direct route as well as the reinstatement of three other direct routes from the Asia Pacific region will further increase the foreign arrivals to Kota Kinabalu International Airport (KKIA).

    ReplyDelete
  2. 11 airlines with a weekly seating capacity of 18,000 will reconnect 13 international cities with Sabah, including Shanghai, Hong Kong, Osaka and Perth.

    ReplyDelete
  3. Malaysia Airline's inaugural flight from Shanghai to Kota Kinabalu on 12.12.12, a most auspicious date of the century, signaled the start of something big for Sabah's tourism industry. Landing on the land below the wind twice weekly, this will be MAS' third international route originating from China after Hong Kong and Shenzhen.

    ReplyDelete
  4. "Shanghai is China's gateway to Sabah," said the Chairman of Sabah Tourism Board (STB), Datuk Seri PanglimaTengku Zainal Adlin, "and a hub that connects Sabah to China's key international financial centres as well as the provinces located in it's eastern region namely Zheijiang, Jiangsu, Anhui and Hubei."

    ReplyDelete
  5. “We are looking ahead to 2013 and beyond. The state government is drawing strategic plans to increase its air accessibility, as 96% of our arrivals are by air," said the Chairman of STB.

    ReplyDelete
  6. Malaysia Airlines have already reinstated the direct routes from Hong Kong and Perth on the 1st and 9th of December 2012, respectively. The Osaka direct route will be reinstated on the 20th of December this year.

    ReplyDelete
  7. Up to October 2012, foreign arrivals to Sabah have increased by 779,845, a 14.5 percent jump compared to the same period last year.

    ReplyDelete
  8. The airport charges in KKIA has been increased to RM65 while RM25 for KKIA Terminal 2, starting Sept 15

    ReplyDelete
  9. Deputy Transport Minister Rahim Bakri hopes the State Government will support the decision to shift all passenger airline operations from Terminal 2 to the KKIA Terminal 1 because the current Terminal 2 is overcrowded and congested

    ReplyDelete
  10. Almost 60,000 aircraft movements were recorded in KKIA last year with almost six million passengers transported in and out of the airport, an increase of 11.2 per cent compared to the previous year.

    ReplyDelete
  11. With more flights expected to touch down at the KKIA, bringing with them the tourism receipts the government has set its sights on, these engineers and technicians are gearing up to meet the demand

    ReplyDelete
  12. There are complaints that the Terminal Two is congested due to the growing number of passengers and it is not equipped with facilities of international standard

    ReplyDelete
    Replies
    1. Pihak berkuasa harus mengambil langkah untuk menyelesaikan kelemahan tersebut.

      Delete
  13. Articles and content in this section of the website are really amazing. Great ideas indeed! I will surely keep these in my mind!

    cpc transport manager

    ReplyDelete